{% if event.permit_required == true %} We are scheduling an inspection with {{customer.AHJ}} to ensure your system is ready to be powered on. Depending on where you live and the details of your system, your system may require more than one inspection prior to approval. {% endif %} We'll need permission from {{customer.utility_company}} to operate your system. This is often called permission to operate or PTO, which, as you may expect, can take some time. In fact, after inspections, waiting for PTO from your utility typically ranges from two to six weeks. Once we get PTO approval we will get your system turned on, build your online monitoring portal and send you instructions on how you can watch your panels producing energy from the sun and saving you money! |